After a year and a half of preparation, this amazing job was completed with the regular team. The entire dome roof was replaced. Not only that, the work took place while at the same time the pools were being renewed and even 5,000 visitors were still walking around until the day the work started.
This challenging lifting project consisted of several phases, each presenting challenges.
The new plastic domes were pre-assembled in 64 modules in the car park outside the park. From there, they were transported to under the crane hook. For hoisting, our engineers developed a special lifting frame, a practical hoisting tool equipped with different coloured lifting eyes that corresponded to the various types of modules. Above this, a balancer was deployed again for efficiently and safely setting the right lifting angle.
Check out the entire report here.