Germany, like the Netherlands, is in the process of expanding its electricity grid. This is the result of increasing demand for electricity combined with a growing supply of sustainably generated energy from (offshore) wind and solar power. These expansion projects sometimes require heavy transformers. And that, in turn, is a great challenge for Wagenborg Nedlift's transformer team!
Twence in Hengelo is building a large-scale CO2 capture plant that will annually capture 100,000 tonnes of CO2 from flue gases. An innovative sustainability project that contributes significantly to reducing CO2 emissions in the region and making the chain more sustainable.
For many years now, Wagenborg Nedlift has had the pleasure of carrying out a wide range of projects for the Genemuiden-based company Breman Machinery B.V., each project more unique than the last. This time round, Wagenborg was tasked with weighing and lifting what is known as an ABIT tool, and transporting it by land and water.
Just last week we began transporting the first of five 380 kV transformers. In the early hours of this morning, the fifth and final transformer was given an official and ceremonial reception at the Vierverlaten high-frequency substation, west of Hoogkerk near Groningen.
For some time now, the high-voltage power network around Antwerp has been undergoing a major enhancement and upgrading project. Elia, the network operator, is constructing various new connections, which means that the high-voltage substations also have to be adapted and expanded.
An exceptional transport operation was carried out in Assen, Drenthe over the past few days. Two transformers, each weighing 250 tonnes, were transported to the site for the expansion of the Zeijerveen transformer station. A skillful piece of heavy transport work!
Breman Machinery in Genemuiden has been busy building a Casing Lifting Adapter over the past few months. This is a lifting tool for the installation of 190 foundation piles for the Saint-Brieuc offshore wind farm that is being constructed off the coast of Brittany (France). Van Oord will take care of the transport and installation of the foundations for this offshore wind farm.
The new Eemshaven - Vierverlaten high-voltage line will see a major expansion of the Vierverlaten high-voltage substation. Six giant transformers will be installed later this year, but first the transformer fields and other installations will be constructed. A transformer cabin housing all the control technology is also being installed at each field.
There was recently a lot of activity at the power distribution station on the Karperweg in Amsterdam. Three transformers were being transported to the station, where they were to be installed.